Project Updates in the City – July 31, 2026

Court / Herbster Street Project – the driveways on the East side of Court Street will not be accessible until approximately mid week next week.

Monday, August 3, 2026 – Crews will be pouring curbs on the East side of Court Street. Crews will also be working on water services on N. Elm Street from East Park Avenue Salem Street.

Tuesday, August 4, 2026 – Crews will be installing the driveway approaches. Approximately 2-3 days after that residents will be able to access their driveways.

Road is closed and open to local traffic only. Residents are welcome to park on Prospect Street, Herbster Street or in the Firestone Park. 

*********************************************************************************************************************************************************

Ray /Beverly Project – Starting Monday, August 3, 2026 East Park will be closed at Beverly Drive – open to local traffic only.

(Access Windsor House, Sitler the Printer, or The Willow Shop from SR 14. Access to Blue Ribbon Chiropractor should be off of Springfield Road.)

*********************************************************************************************************************************************************

Firestone Park Phase 2 Project – Use CAUTION when entering the Firestone Park. Crews are working from Pavilion #4 to Pavilion #1 to the locker rooms area and then over to Pavilion #3.

 

We appreciate your patience and understanding while these projects are completed!

 