UPDATE: Wednesday, June 22, 2022
All N. West Street residents are now being asked to park on W. Salem Street by 7am on Thursday, June 23, 2022.
Cement Trucks will arrive by 7am on Thursday, June 23, 2022 for curb installation and all cars need to be off the street to allow the cement truck crews enough room to pour the curbs.
Parking will be allowed on N. West Street once all curbs are complete.
Once curbs are poured you will not be able to drive on them for 2 days.
UPDATE: Monday June 16, 2022
Curb installation on the West side of N. West Street will begin on Wednesday, June 22, 2022 and the East side of N. West Street will be begin on Thursday, June 23, 2022.
Residents should park on the opposite side of the street while the curbs are being installed on their side of the street. You may park on your side of the street once complete. Once curbs are poured you will not be able to drive on them for 2 days.
PARKING ON W. SALEM STREET, ON THE SOUTH SIDE OF THE STREET, IS BEING ALLOWED UNTIL THE NEW CURBS AND BLACKTOPSS ARE COMPLETE ON N. WEST STREET.
UPDATE: Monday June 6, 2022
No work is expected on N. West Street on Tuesday, June 7, 2022. On Wednesday, June 8, 2022, crews will be digging out roadway to make repairs. Depending where you live on N. West Street, you may have to exit/enter from Salem Street. This work will continue for the remainder of the week.
On Monday, June 13, 2022 crews plan to start pouring the curb on N. West Street and is expected to take two days. We will post updates on curb pouring later this week.
UPDATE: Thursday MAY 19, 2022
The road surface removal on N. West Street will begin on Monday, May 23, 2022 at 8AM. The road will be a slag surface for approximately 10 days.
UPDATE: Tuesday APRIL 19, 2022
Due to the weather conditions, backfilling on the East side of N. Pearl Street should be finished up today and tomorrow. And the curb pouring on the West side of N. Pearl Street should be completed by Thursday April 21st.
Also, Milling on West Salem Street will now begin on Wednesday April 20th and paving of West Salem Street and N. Pearl Street will most likely start the first of next week.
UPDATE: Monday APRIL 18, 2022
Due to the weather conditions today, curb replacement on the East side of N. Pearl Street will resume on Tuesday April 19th and will be completed Wednesday April 20th. Residents will need to park on the West side of N. Pearl Street until pouring is complete, once complete residents may park on either side of the street until driveway entrance is allowed.
UPDATE: Friday APRIL 15, 2022
Milling on West Salem Street will begin on Tuesday April 19th and paving of West Salem Street will be done on Wednesday April 20th.
Paving on N. Pearl Street will begin on Thursday April 21st and will be finished up on Friday April 22nd.
UPDATE: Wednesday APRIL 13, 2022
Curb replacement on the West side of N. Pearl Street will be done on Thursday.
Curb replacement pouring on the East side of N. Pearl Street will begin on Friday and continue on Monday. Residents will need to park on the West side of N. Pearl Street until pouring is complete, once complete residents may park on either side of the street until driveway entrance is allowed.
UPDATE: STARTING Wednesday APRIL 13, 2022 @ 8AM:
On Wednesday, April 13, 2022 Curb Replacements will begin on the West side of N. Pearl Street. Driveways will be blocked off until Friday, April 15, 2022 and residents will need to park on the East side of N. Pearl Street during this time.
Then, beginning on Friday, April 15, 2022 the Curb replacements will begin on the East Side of N. Pearl Street. Driveways will be blocked off until Tuesday, April 19, 2022 and residents will need to park on the West side of N. Pearl Street during this time.
UPDATE: STARTING Monday MARCH 28, 2022 @ 8AM:
The road surface removal on Pearl Street between West Park Avenue and Salem Street will begin on March 28, 2022 at 8AM. The road will be a slag surface for approximately 3-4 weeks.
UPDATE: STARTING FRIDAY MARCH 11, 2022 @ 8AM:
Pearl Street will be closed from West Park Avenue to Salem Street starting at 8AM on Friday March 11, 2022, open to local traffic ONLY until further notice.
UPDATE: STARTING FRIDAY DECEMBER 17, 2021 @ 4PM:
West Salem Street will be open starting at 4PM on Friday December 17, 2021 for thru traffic.
N. Pearl will remain closed, open to local traffic only until further notice.
UPDATE: STARTING MONDAY DECEMBER 6, 2021:
Starting Monday December 6th – West Salem Street and North Pearl Street will be closed at that intersection.
Access to Old North will be from Main Street ONLY.
This closure will be for the entire week December 6-10, 2021.
UPDATE: STARTING WEDNESDAY NOVEMBER 24, 2021:
Pearl Street will be closed to through traffic.
Northwest Street, Allen Avenue and Middle Street will be OPEN.
West Salem Street will remain closed, open to local traffic only.
Entrance to Old North needs to be accessed from Main Street.
UPDATE: STARTING FRIDAY NOVEMBER 5, 2021:
Pearl Street will be closed to through traffic.
Northwest Street, Allen Avenue and Middle Street will be OPEN.
West Salem Street will remain closed, open to local traffic only.
As of October 14, 2021 – November 4, 2021
West Salem Street is still limited to local traffic only.
Entrance to Old North needs to be made from Old Route 14.
Middle Street is now open to access Joshua Dixon School from Main Street.
Allen Avenue is closed at Middle Street (between Middle and Northwest)
This will continue until further notice.
Please contact City Hall at 330-482-2173 option 6 with any questions or concerns.